Since our September updates on Queensland’s planning framework for data centres and the proposed national standards, the Queensland Government has announced that it will take the planning and assessment of data centre applications away from local councils, under a system set to start in the coming weeks. The Government has said the new framework will follow its reforms for renewable energy projects. To understand what is coming, it helps to look at how that renewables pathway works now. This article considers what that model may mean for data centre proponents, local governments and applications already underway.
The announcement
“If data centres want to do business in Queensland, here’s the non-negotiables: you’re not going in people’s backyards, you’re not pinching our power, and you’re not shipping our data off overseas,” Premier David Crisafulli said. He added that data centre investment must create local jobs and help bring electricity bills down.
Before lodging a development application, a data centre developer will have to complete a social impact assessment and enter into a community benefit agreement with the local council. The Government’s reason for the change is that many councils’ planning schemes do not deal with data centres, which has caused confusion and inconsistent outcomes.
The proposed approval pathway
The detail of the new framework has not yet been released. However, the Government has indicated that it will draw on the approval pathway introduced for renewable energy projects. That pathway works in two layers. Part 6B of the Planning Act 2016 (Qld), which commenced on 18 July 2025, sets out the rules for social impact assessment reports and community benefit agreements, and allows a regulation to prescribe the development to which it applies. The Planning Regulation 2017 (Qld) then names that development (currently wind farms, solar farms of 1MW or more and battery storage facilities of 50MW or more) and makes the State Assessment and Referral Agency (SARA) the assessment manager. Because the Regulation can be amended without legislation, data centres could be brought into the system relatively quickly.
Compared with a standard development application, the pathway has several distinctive features. Applications are impact assessable against State codes. Neither the absence of a community benefit agreement nor its inadequacy is a ground for refusal, except where the application has been called in by the Minister. The chief executive may also waive the need for a social impact assessment report or community benefit agreement and may refer stalled negotiations to mediation.
If adopted for data centres, the final framework will need to identify which projects are captured (including any size threshold), the assessment requirements that will apply and how existing applications will be treated. These details are likely to be addressed in an amending regulation and transitional provisions.
What it means for data centres
If the Government adopts the renewables model, data centre proponents may need to prepare for three things:
- first, there will be more work before lodgement, including preparation of a social impact assessment report and a community benefit agreement (which must be in place before the application is ‘properly made’). The agreement is made with the local council, and also with any neighbouring council whose community is affected;
- second, applications will be subject to mandatory impact assessment; and
- third, submitters will gain third-party appeal rights, although they cannot appeal community benefit conditions imposed under s 65AA (s 106ZJ).
For new applications, and subject to any transitional arrangements, local governments would no longer be the assessment manager for data centres, although they would remain parties to the community benefit agreement.
The Western Downs Digital Park
The announcement comes as the Western Downs Regional Council assesses Zerra DC’s proposed Western Downs Digital Park near Dalby, valued at about $32 billion, with Anthropic signed to lease the first of four planned buildings. The council has no firm timeframe for its decision. Mayor Andrew Smith has said the State has assured the council that it will remain the assessment manager for the project.
How existing applications are handled will matter a great deal. When the renewables changes commenced, undecided applications were treated as not properly made unless they were already subject to a call in or direction notice. Whether similar transitional rules apply to data centres, and whether they are consistent with the assurance given to the Western Downs Regional Council, remains to be seen.
What to watch
Proponents and local governments should watch for the amending regulation, any size threshold and transitional provisions, and the outcome of Zerra DC’s prescribed project request. Proponents considering a Queensland data centre project should assess now how the proposed changes may affect site selection, development timeframes, community engagement and applications already in preparation or assessment.
McCullough Robertson’s planning, environment, energy and infrastructure teams advise proponents and local governments on major project approvals, social impact assessment, community benefit arrangements and regulatory change. We can assist clients to review their approval strategy and prepare for the new framework as further detail becomes available.